How to Build Concrete Steps

To build concrete steps, lay out risers of 7 3/4 inches or less, all within 3/8 inch of each other, pour a footing below the frost line, form the sides and risers, fill the core with gravel, set rebar, pour from the bottom step up, then strip the riser boards early to finish them. The hard part is finishing each tread behind a riser form before the concrete sets.

How to pour concrete steps, step by step

Do them in this order: the rise you work out in step 1 sets every form dimension after it.

  1. Work out the rise. Divide the total height from landing to grade by the riser count, keeping each riser at 7 3/4 inches or less, and build every step to that figure, even if it's 6 13/16 inches. Don't let the bottom step soak up the leftover.
  2. Pour the footing. In a frost climate, steps sit on a footing below the frost line, which can take as much concrete as the steps. Get the depth from your building department, size the footing on its own, and isolate it from the house with expansion material.
  3. Build the forms. Cut each side cheek to the full stepped profile from 3/4 inch plywood or 2x stock, and span riser boards ripped from 2x material between them. Stake every couple of feet and brace any riser board over about 4 feet wide at mid-span.
  4. Fill and reinforce. Fill the core with compacted gravel (the gravel calculator sizes it), then run rebar through the risers and treads and down into the footing, with good cover over the steel. The rebar calculator counts bars.
  5. Pour from the bottom step up. Fill, consolidate and strike off each step before the next, working the concrete along each riser face so it doesn't honeycomb.
  6. Strip the riser boards early and finish. Pull them while the concrete is still workable, float the riser face, broom the tread across the direction of travel and round the tread edge with an edger.
  7. Cure. Steps dry from three sides at once and craze if they aren't kept wet or covered; concrete cure time covers how long.

Mixing it by hand is slow. For a DIY pour, a 4 ft set of three 7 inch risers with 11 inch treads and no landing is about 0.48 cubic yards poured solid, roughly 22 bags of 80 lb mix, and a cold joint shows on every riser face. A 36 inch landing roughly doubles that. If the footing goes in the same day, order ready-mix; delivery minimums and short-load fees explain the cost.

Rise and run the code allows

Risers can be at most 7 3/4 inches under IRC R311.7.5.1 (R318.7.5.1 in the 2024 edition), and the tallest can't beat the shortest by more than 3/8 inch, which the bottom step usually breaks. Boise's treads and risers handout sets out both.

Two side profiles of three concrete steps rising 21 inches, drawn to scale. Divided evenly, each riser is 7 inches and passes. Built as two 7 1/2 inch risers with a 6 inch bottom step, the spread is 1 1/2 inches and fails the 3/8 inch limit.
Divide the total rise evenly; letting the bottom step take the leftover fails.
  • Tread

    10 in min

    At 11 inches or more you need no nosing, which simplifies the forms.

  • Handrail

    4 risers

    Required at four or more risers, per Spokane County. Price both layouts with what steps cost.

  • Guard

    30 in

    Required once the walking surface is more than 30 inches above grade within 36 inches of it.

  • Good work

    1/16 in

    Between consecutive rises in the federal formwork spec UFGS 03100A, far tighter than the code allows.

The stairs calculator gives the volume, weight and every IRC dimension for your layout.

Forms for concrete steps

Stair forms are two side cheeks cut to the stepped profile plus one riser board per step. ACI 347 gives no stair-specific form design, so lumber sizes here are trade practice.

Section through three formed concrete entry steps against a house. A footing below the frost line carries the front. The core is compacted gravel fill under a concrete shell with rebar running through it. Riser boards form each riser face with the bottom edge beveled, and a stake and kicker brace the bottom board. A landing at least 36 inches deep sits at the door, an isolation joint separates the steps from the house wall, risers are 7-3/4 inches or less and within 3/8 inch of each other, treads are 11 inches or more so no nosing is needed, and treads pitch forward about 1/4 inch per foot.
How the parts of a formed concrete step go together, in section. Tap to enlarge.

Bevel the riser boards or not? Beveling the bottom edge lets a float reach the back of the tread before stripping, which is why Fine Homebuilding recommends it; others skip it and finish after pulling the boards early. That bevel is separate from the 1/4 inch per foot forward pitch on each tread for drainage, which the slope calculator converts.

Best concrete for steps

In a freeze-thaw climate, use 4,000 psi air-entrained concrete. Steps are in the IRC's toughest residential exposure row, with air required in moderate and severe climates.

The concrete mix calculator matches mixes to jobs, and the bag calculator turns the stairs volume into bags.

Building concrete steps on a slope

Garden steps that don't serve a building, porch or deck are exempt from the IRC stair rules (R311.7), and they feel best with lower risers and longer treads than entry steps.

Pittsburgh builds its public steps on grade at a 6 to 7 inch rise with 12 to 24 inch treads on compacted subbase. Pick a riser near 6 inches, size the tread from the rule, and add landings rather than stretching treads between one stride and two. Pitch each tread forward and give water a way off the sides; cinder block steps are a dry-laid alternative that drains through the cores.

Patio steps and single steps

The rules that matter at a patio door are about the landing. It can sit at most 1 1/2 inches below the threshold, with exceptions when the door doesn't swing over the step.

  • One riser down

    Allowed

    At the main exit if the door doesn't swing over the landing, and at other exterior doors regardless of swing, per Indiana's reprint of IRC R311.3.

  • No top landing

    Up to 2 risers

    If the door doesn't swing over the stairway, per Jefferson County, Colorado. An outswing storm door usually rules this out.

Avoid a single step: Texas A&M calls for at least two to avoid an "invisible one-step hazard." Ask your building department whether patio-to-yard steps count as part of the house, since the stair exemption names porches and decks, not patios.

  • Isolate new steps

    Joint

    NRMCA's joint guidance lists stairs among points that need an isolation joint, so don't tie new steps into an old slab.

  • Keep siding clear

    2 in

    Wood within 2 inches of concrete steps must be treated or protected under IRC R317.1, per Middleton, Idaho.

Other ways to build concrete steps

For treads that seem to hover, see floating concrete steps; for one-piece units set by a boom truck, precast concrete steps.

Next

Price the job or check a ramp before you dig.

Worn steps can often be saved: how to resurface concrete steps. A step at a shed door is covered in the shed slab guide.

Frequently asked questions

How do you build concrete steps?

Lay out an even rise of 7 3/4 inches or less per step, pour a footing below the frost line, form the side cheeks and riser boards, fill the core with compacted gravel and set rebar, pour from the bottom step up, strip the riser boards early to finish the faces, and cure.

Do concrete steps need rebar?

Yes in practice. Rebar runs horizontally through the risers and treads and vertically into the footing, with good cover over it, because steps get standing water and de-icing salt.

Do you pour concrete steps solid?

Usually not. A core of compacted gravel under a concrete shell is normal and saves concrete and weight: a 4 ft set of three risers with no landing is about half a cubic yard poured solid, close to a ton.

Should the riser form boards be beveled?

Either works. Beveling the bottom edge lets a float reach the back of the tread before the boards come off, which is why Fine Homebuilding recommends it; others finish after stripping the boards early.

When do you strip the forms on concrete steps?

Pull the riser boards early, while the concrete is still workable, so the faces can be floated. That is stripping to finish the surface, not structural form removal, and ACI 347 gives no stair-specific guidance.