Floating Concrete Steps: How They Are Built

Floating concrete steps are usually ordinary slab steps on a base set back from the front and sides, so a shadow line makes each step look like it hovers. The overhanging lip is a short cantilever, so its steel goes near the top, not the bottom. True floating stairs, with treads cantilevered from a wall and nothing underneath, are structural work and need an engineer.

The two kinds of floating step

Most outdoor floating steps are the recessed-base kind: supported from below, with only the front lip overhanging. Cantilevered treads have nothing underneath at all.

Side sections to scale with 7-1/2 inch risers and 12 inch treads: recessed-base steps sit on a base set back under each slab so only the front lip overhangs, while cantilevered treads stick out from a wall with nothing underneath and need an engineered design.
  • Recessed base

    DIY

    Ordinary steps with one extra form. Everything in how to build concrete steps still applies.

  • Cantilevered tread

    Engineered

    Fixed into a wall or a central spine at one end, and outside the IRC's prescriptive rules.

Steel goes on top in the overhang

An overhang bends the opposite way to a slab on the ground: in a cantilever "the top face is in tension, in contrast to the simply supported beam where the bottom face is in tension" (Princeton CASCE). Bars that sag to the bottom do nothing in the lip.

To scale section of a 5 inch tread lip: the overhang puts the top face in tension, so the bar sits near the top with 1-1/2 inches of cover and runs back over the base to anchor.
  • Cover

    3 in against earth

    And the 1-1/2 in shown for No. 5 and smaller bars exposed to weather (IRC R403.1.3.5.3, ICC text).

  • Chairs

    Tied high

    Hong Kong's cantilevered slab note warns against bars being "displaced or depressed." Check them before the pour.

  • Anchorage

    Back over the base

    The same note says main bars must be properly anchored into the supporting structure.

No standard sets a minimum floating tread thickness; the top cover, the bar and concrete below it set the practical minimum. The rebar calculator totals the bars.

Building recessed-base floating steps

Form the recess with a foam block-out in one pour, or pour the bases first and the tread slabs on top; two pours is easier for most people.

  • One pour

    Foam block-out

    Fix rigid foam where the recess goes, with a release rated for EPS, such as Nox-Crete's foam form release.

  • Two pours

    Bases, then treads

    Set the bases back, then pour each tread with bars coming up out of the base and a removable board under the lip.

  1. Lay out the steps. Work to the limits in dimensions below, and mark the setback for each base.
  2. Build the bases. Put them on footings protected from frost (IRC R403.1.4.1); the footing calculator sizes them.
  3. Form the overhang. Set the block-out or the lip board, then the riser and side forms.
  4. Put the steel near the top. Tie it on chairs and check its height just before the pour.
  5. Leave the support in and cure. Strip the riser faces to finish them, leave the lip board, and keep the concrete moist.

The board under the lip carries load. OSHA's rule for contractors, 1926.703(e)(1), keeps such forms in place until the concrete "has gained sufficient strength to support its weight and superimposed loads." Riser faces come off in hours for finishing; the lip support stays.

ACI's slab guide, as quoted by the ASCC, recommends curing 7 days above 40 degrees F; cure time covers the methods.

True cantilevered treads need an engineer

IRC R301.1.3 sends anything outside the code's prescriptive limits to engineered design: it must be "designed in accordance with accepted engineering practice" (Seattle's 2021 code, chapter 3).

  • Stair load

    40 psf

    IRC Table R301.5 live load for stairs.

  • Each tread

    300 lb

    A concentrated load on 4 sq in, whichever governs. A load at the tip is resisted where the tread enters the wall.

  • Open risers

    4 in sphere

    Above 30 in, gaps can't pass a 4 in sphere (IRC R311.7.5.1, per Placer County).

The dimensions are the same as any other step

A floating look doesn't change the stair rules for steps serving a door.

  • Riser

    7-3/4 in max

    Within 3/8 in of each other (Placer).

  • Tread

    10 in min

    11 in and up needs no nosing, per Placer.

  • Landing

    36 in

    Deep at the door (IRC R311.3).

  • Handrail

    4 risers

    Needed at four or more (Okanogan County).

Concrete = full step volume minus the recess volume

The stairs calculator gives the full step volume; subtract the recess. Building the base from block instead? See cinder block steps.

Frequently asked questions

How are floating concrete steps supported?

Most sit on a smaller base set back from the front and sides, so only the lip overhangs. True floating stairs are cantilevered from a wall or a central spine with nothing under each tread, which takes an engineered design.

Where does the rebar go in a floating step?

Near the top, with at least 1-1/2 inches of cover where it is exposed to weather, and running back over the base. The overhang is in tension on its top face, so bars at the bottom do nothing there.

Do floating concrete stairs need an engineer?

True cantilevered treads do: the IRC has no prescriptive design for them, and each tread has to carry a 300 pound concentrated load. Recessed-base steps with a short overhang are ordinary steps and usually do not.

How thick should a floating concrete step be?

No standard sets a minimum. Top cover of 1-1/2 inches plus a 1/2 inch No. 4 bar is already 2 inches before any concrete below the bar, so the lip ends up several inches thick; an engineer sizes a true cantilever.

Can I use foam to make floating concrete steps?

Yes. A rigid EPS foam block-out inside a full step form makes the recess in one pour; use a form release rated for EPS so the foam comes away cleanly.