How Long Does Concrete Take to Cure?

Concrete takes 28 days to reach its design strength, but it has about 75 percent of it at 7 days and you can walk on it after a day or two. The concrete cure time that matters most is that first week, when the slab has to stay moist. Drying, water leaving the slab, comes after curing and only matters before flooring goes down.

When can you walk and drive on new concrete?

Walk on it after a day or two and drive a car on it after a week, if the weather is mild. Flooring is the exception: it waits for a moisture test, not a date.

Timeline for new concrete at about 70 degrees F: sets in about 6 hours, side forms off at 1 day, walk on it at 1 to 2 days, stop curing and drive a car at 7 days, design strength at 28 days, and dry enough for flooring only after a moisture test, often 6 weeks or more.

The walk, drive and heavy truck times are rules of thumb, not standards. A Minnesota DOT study on concrete strength required to open to traffic found states opening engineered pavements in as little as 6 to 8 hours at around 3,000 psi, and found current opening methods often overly conservative. For a bagged-mix driveway, keep the week.

Setting, curing and drying are three different clocks

Concrete sets in hours, cures over about a week and dries for months. Only curing makes it stronger.

  • Set

    Hours

    Goes from plastic to solid. It can be walked on long before it's strong.

  • Cure

    7 days

    Keep it moist and above 50°F so the cement keeps reacting, per ACI's definition of curing.

  • Dry

    6 weeks +

    Water leaving the slab. Only matters before flooring goes down.

Strength gain stops once the slab's internal humidity drops to about 80 percent, per the PCA's Design and Control of Concrete Mixtures.

Concrete strength by day

Concrete gains most of its strength in the first week: a 5,000 psi mix cured at 73°F is at about 3,250 psi on day 3 and 3,750 on day 7, per the Federal Highway Administration's materials course.

Graph of concrete compressive strength as a share of 28-day strength against age in days. Typical concrete cured at 73 degrees F reaches about 65 percent at 3 days, 75 percent at 7 and 100 percent at 28, per FHWA. Quikrete 5000 reaches 30 percent at 1 day, 50 at 3, 70 at 7 and 100 at 28, from its data sheet. A marker at 28 days shows concrete left to dry in air the whole time can reach as little as about 50 percent of moist-cured strength.
Typical concrete per FHWA; Quikrete 5000 per its data sheet.

28 days is a testing convention, not a finish line. The industry picked it as a standard test age, as the National Precast Concrete Association explains in its piece on the 28-day myth. Concrete keeps gaining strength after that as long as it has moisture.

When to remove concrete forms

Side forms can come off after 12 to 24 hours; forms that hold concrete up from underneath stay 4 to 7 days on spans under 20 ft, longer on long beams. OSHA 1926.703(e) ties removal to strength, not the calendar, and NRMCA puts the practical range at 1 to 7 days depending on rate of strength gain.

Minimum times from Michigan State University's formwork standard, which follows the ACI 347 pattern:

  • Wall and beam sides

    12 to 24 h

    They carry no weight, only the concrete's shape.

  • Slab underside, under 10 ft

    4 days

    3 if live load exceeds dead load.

  • Slab underside, 10 to 20 ft

    7 days

    4 if live load exceeds dead load.

  • Beam and joist undersides, under 10 ft

    7 days

    4 if live load exceeds dead load.

Side forms on a slab, footing, curb or step hold nothing up, so they're the 12 to 24 hour case. The overhang of a step or a suspended slab is the multi-day case.

Only warm hours count. Collierville, Tennessee's ACI 347-based formwork spec lets side forms come off "after cumulatively curing at not less than 10 °C (50 °F) for 24 hours." Hours below 50°F don't count, so in cold weather side forms stay on until the concrete has had 24 hours of protection at 50°F or warmer.

How to cure a concrete slab

Keep it moist for 7 days, starting as soon as the surface is firm. NRMCA's CIP 11 on curing in-place concrete puts the practical range at 3 to 7 days.

  1. Start as soon as the surface is firm. Begin once you can't mar it, right after finishing.
  2. Keep moisture in for 7 days. That's the ACI 308.1 default above 50°F, and it lets curing stop early once the concrete reaches 70 percent of its specified strength.
  3. Pick one method and stick to it. A sprinkler or wet burlap kept wet, plastic sheeting at least 4 mils thick, or a spray-on curing compound. Leaving forms on also holds moisture in.
  4. Protect it from the weather. Below 40°F, cover it; in heat and wind, dampen the subgrade before the pour and get the cover on early.
  5. Test before covering it. Before tile or flooring, run a moisture test instead of counting days.

Wetting it once and letting it dry doesn't count as curing. CIP 11: "Alternate wetting and drying is not an acceptable curing practice." How to cure concrete covers each method, watering schedules and curing compound coverage.

What happens if you skip curing

You lose strength: 16 percent in FHWA's lab comparison, and up to half in a dry environment, per NRMCA.

  • Worst case

    50% weaker

    Concrete left in a dry environment, per NRMCA's CIP 11.

  • Lab, air-cured

    16% weaker

    FHWA's comparison: about 4,200 psi with poor curing against 5,000 with good curing at 28 days.

Surfaces dry first, so poor curing shows up as crazing, dusting and scaling. On a dry, breezy pour day, water can leave the surface before the concrete sets and cause plastic shrinkage cracking.

How temperature changes concrete cure time

Every 20°F drop roughly doubles the setting time, per NRMCA's CIP 27. Penn State's setting time table is charted below.

Bar chart of concrete setting time by concrete temperature: about 1.7 hours at 100 degrees F, 2.7 at 90, 4 at 80, 6 at 70, 8 at 60, 11 at 50, 14 at 40 and 19 at 30; at 20 degrees F it does not set.
  • Cold: below 40°F

    500 psi

    Keep it from freezing until it gets there, about 2 days after placement. Frozen fresh concrete can lose over half its strength (NRMCA CIP 27). Full detail: pouring concrete in cold weather.

  • Hot weather

    3 days

    Minimum cure, with the subgrade dampened first. Hot early curing means lower later strength (NRMCA CIP 12).

How long before you can tile or floor over it?

Six weeks to a year or longer, says NRMCA's CIP 28 on slab moisture, so test the slab instead of counting days.

  • Calcium chloride test

    3 to 5 lb

    ASTM F1869 limit, per 1,000 sq ft per 24 hours, read over 60 to 72 hours.

  • Relative humidity probe

    75 to 80%

    ASTM F2170 typical target, measured inside the slab at depth.

Basement slabs keep getting vapor from below; the basement concrete floor guide covers testing them.

How the mix changes the timeline

High early strength cement and high strength bagged mixes get there faster; fly ash and extra water slow things down.

Most US cement is now Type IL, which PCA says performs comparably to portland cement; our Type IL piece covers the one place it differs, the first winter.

Cure times don't change with volume. Size the pour with the concrete slab calculator or the concrete floor calculator, check concrete slab thickness, and follow how to pour a concrete slab on the day. Sakrete's mixes are in the Sakrete mix types guide, and dry pour concrete explains why skipping the mixing step causes curing trouble. For how concrete got here, see our history of concrete.

Frequently asked questions

How long does concrete take to cure?

Keep it moist for 7 days; by then it has about 75 percent of its strength. It reaches design strength at 28 days, the standard test age, and keeps gaining slowly after that.

How long before you can walk on new concrete?

24 to 48 hours in mild weather. That is a contractor rule of thumb, not a standard, so give it longer when it is cold: NRMCA says setting time roughly doubles for every 20 degree F drop.

How long before you can drive on new concrete?

Seven days for a car on a residential driveway, and 28 days for heavy trucks or an RV, both rules of thumb. Highway agencies open engineered pavements much sooner, at around 3,000 psi, because strength is what counts, not days.

How long does concrete take to dry?

Six weeks to a year or longer before it is dry enough for flooring, depending on thickness and conditions. It sets in hours and is walkable in a day or two, but that is not the same as dry.

Can you pour concrete in cold weather?

Yes, with protection. Keep fresh concrete from freezing until it reaches 500 psi, about two days after placement, because concrete that freezes early can lose more than half its strength. Pouring concrete in cold weather has the full detail.

What is the difference between concrete curing and drying?

Curing keeps water in so the cement can keep reacting; drying is water leaving. Strength gain stops once the internal humidity drops to about 80 percent, so cure first and dry after.