Ready-Mix Concrete Delivery

Ready-mix concrete delivery: delivered ready-mix averaged about $160 a cubic yard in 2023, the industry's average selling price (NRMCA), plus a short-load charge on anything under the producer's threshold. You order by strength, slump, air and quantity, and the load has to be placed within the time printed on the ticket, often 60 to 90 minutes in state specs. A small pour often costs more in fees than in concrete, so the questions you ask the plant matter.

What to specify when you order

Give the plant four numbers: strength, slump, air and quantity, from NRMCA's CIP 31, Ordering Ready Mixed Concrete. Work out the volume first with the concrete calculator.

  • Strength

    3,500 to 5,000 psi

    "Typical for most concrete applications." See concrete psi.

  • Slump

    3 to 5 in

    "For most applications," per CIP 31.

  • Air

    6%

    With 4,000 psi for exterior slabs facing freezing and salt (NRMCA CIP 2).

  • Quantity

    +4 to 10%

    Over the volume from the plan dimensions.

Also give the address, what you're pouring, how fast you can place it and when. Keep the aggregate smaller than the narrowest gap it has to flow through. The producer owns the slump "for a period of 30 minutes after the requested time or the time the truck arrives at the site, whichever is later."

What delivery costs

Ask the plant what's in its yard price and what goes on top for a small load.

Our calculators' own assumption: $125 a yard for the concrete + $35 delivery = $160 delivered
Plus $30 a yard under a 10 yard load

Concrete price per yard explains why published prices disagree, and the concrete cost calculator prices your volume.

The fee schedule

The charges that decide a small pour are the short-load fee and the unloading allowance. Two producers that publish theirs:

  • Cemstone

    6-1/4 yd or less

    Part-load charge on 6-1/4 yd or less; $200 an hour after 7 minutes per yard (dispatch guidelines).

  • Duininck

    $150 to $175

    Short load on 0 to 4 yards; $3 a minute after 8 minutes per yard (customer handbook).

Bars showing free unloading time at 7 minutes per cubic yard (Cemstone) and 8 minutes per cubic yard (Duininck): 14 to 16 minutes for 2 yards, 28 to 32 for 4, 42 to 48 for 6, 56 to 64 for 8 and 70 to 80 for 10.

Also ask about environmental or energy fees (Robertson's, for one, bills them per load), Saturday delivery, winter hot water and accelerators.

Minimum loads and short-load fees

A full truck is usually called 10 yards, but NRMCA's survey participants averaged 8.5 yards a delivery, and 400 million yards in about 50 million trips is 8 a load.

  • Flat fee

    $87.50 a yard

    Duininck's $175 on a 2 yard load. A flat fee costs the smallest pours the most per yard.

  • Per yard

    $30 a yard

    The model our calculators use under 10 yards.

Minimum quantity, short-load threshold and truck capacity are three different numbers; see what the truck minimum really means, and how many yards are in a truck of concrete covers capacity.

Mini mix and volumetric trucks

For a small pour, a smaller drum truck or a volumetric mixer can beat a short-load fee on a full truck.

  • Mini mix

    3 to 4 yd

    Drum sizes on the Terex Advance Cadet (Mini-Mix), a smaller drum truck.

  • Volumetric

    Mixed on site

    Materials stay separate until mixing at the pour. Cemen Tech's M60 carries 8 to 10 yards and makes up to 60 an hour.

Smaller still, bags: 27 ÷ 0.60 cubic feet a bag (Quikrete) is 45 bags of 80 lb mix a yard, about $281. See the bags per yard guide.

The discharge clock

ASTM C94 dropped its default 1-1/2 hour discharge limit in 2021: the purchaser states the limit, or the producer sets it, and it goes on the delivery ticket (NRMCA).

Timeline from adding the mixing water: Wisconsin and Georgia DOT specs allow 60 minutes to discharge, or 90 minutes with a retarder; since 2021 ASTM C94 has no default limit, so the limit is on the delivery ticket.
  • DOT specs

    300 revolutions

    Wisconsin DOT: "Do not exceed 300 total revolutions per batch." Georgia DOT also caps concrete at 90 °F.

  • State specs

    60 to 90 min

    Wisconsin and Georgia allow 60 minutes, or 90 with a retarder; your ticket sets the limit for your load.

Can the truck reach your pour?

Plan for a truck up to 8 feet 6 inches wide: FHWA caps width at 102 inches, and state height limits run 13.6 to 14.6 feet, about 13 ft 7 in to 14 ft 7 in.

  • Chute

    Ask the plant

    Reach depends on the truck's chutes and where it can park; measure from that spot.

  • Too far

    Pump or barrow

    Book a pump in advance, or move it by wheelbarrow inside the free unloading time.

Past the free minutes, waiting is billed: $200 an hour at Cemstone, $3 a minute at Duininck. If barrows can't keep up, book a pump or more hands.

Washout and cleanup, and whose job it is

Agree a washout spot with the driver that's well away from drains and water, per the EPA's washout fact sheet.

  • pH

    Near 12

    Drain cleaner is 13.5; freshwater life needs 6.5 to 9.

  • Distance

    50 ft

    From storm drains, open ditches and water bodies.

  • Capacity

    75%

    Empty it before it's fuller than that; inspect daily.

The EPA says "concrete washout requirements should be included in contracts with concrete delivery companies," so agree the spot with the plant when you book.

What to have ready before the truck arrives

  1. Calculate the volume and add an overage. 4 to 10%, with the main calculator or the slab calculator.
  2. Specify the mix. Strength, slump, air and aggregate size, when you book.
  3. Ask how the fees are structured. Short-load threshold, flat or per yard, and the free unloading minutes.
  4. Check the truck can reach the pour. Width, overhead clearance and chute reach; book a pump if not.
  5. Have the site and the crew ready. Forms braced, steel chaired, base damp, washout agreed, tools out and enough hands. Read how to pour a concrete slab and concrete cure time first.

Frequently asked questions

How much does concrete delivery cost?

Delivered ready-mix averaged $160 a cubic yard in 2023, the industry's average selling price. Small loads add a short-load fee, such as Duininck's $150 to $175 on 4 yards or less.

What is the minimum concrete delivery?

It depends on the producer. A full truck is about 10 yards, but short-load charges start at different thresholds, such as 6-1/4 yards at Cemstone, and many plants will deliver less for a fee.

How long can concrete stay in the truck?

As long as the limit printed on the delivery ticket. ASTM C94 no longer sets a default; state DOT specs such as Wisconsin's and Georgia's allow 60 minutes, or 90 with a retarder.

How long do I get to unload the truck?

Producers allow a set time per yard before billing waiting time: 7 minutes a yard at Cemstone and 8 at Duininck, which charges $3 a minute after that. A 6 yard load gets about 42 to 48 minutes.

Is mini mix or a volumetric truck cheaper for a small pour?

Often. A mini mix drum truck carries 3 to 4 yards and fits where a full truck can't, and a volumetric truck mixes on site from separate materials; compare both against your plant's short-load fee.

Where should the truck wash out?

Not near a drain: EPA says washout areas should be at least 50 feet from storm drains, ditches and water, because the water has a pH near 12. Agree the spot when you book.