Concrete Slope Calculator

This concrete slope calculator works out the concrete for a slab that's thicker at one end, which is what you pour when you pitch the top for drainage. Enter the run (the direction the water falls), the width, and the thickness at the low and high ends, and it averages the two for cubic yards with waste, bag counts in 80, 60 and 40 lb sizes, and the weight. Leave the high end blank for a slab of constant thickness.

Sloped pour calculator

Estimated concreteEnter your dimensions above

Enter both thicknesses and the calculator averages them, which is the correct treatment for a tapered pour. Leave the high end blank for a slab of constant thickness.

How to use it

Fall (in) = run (ft) × slope (in per ft)

  1. Pick the direction the water goes. The run is measured that way, not along the longest side.
  2. Work out the fall. A 12 foot patio at 1/4 inch per foot needs 3 inches.
  3. Pitching the top over a flat base? Enter your slab thickness at the low end, and that thickness plus the fall at the high end.
  4. Pitching the base instead? Leave the high end blank. The slab is the same thickness everywhere, so the volume is the same as a flat slab; the slab calculator adds reinforcement and base.

How much slope does a slab need?

Use a quarter inch per foot on exterior slabs: ACI 302.1R sets forms and screeds "to provide for a minimum slope of 1/4 in. per ft (20 mm/m) to prevent ponding." Some groups accept half that.

  • ACI 302.1R

    1/4 in per ft

    Minimum for positive drainage, which it says exterior slabs should always have.

  • Michigan Concrete Assn.

    1/8 in per ft

    Minimum for driveways and sidewalks, in its 2025 guidelines.

  • IRC R401.3

    2%

    For paving within 10 feet of a house, sloped away from it; bare ground needs 6 inches of fall in those 10 feet. The DOE's Building America guide explains both.

  • Garage floors

    No number

    IRC R309.1 only says slope to a drain or the door. See garage floor and garage slab.

Scale from 0 to 3 percent: 1/16 inch per foot, 0.52 percent, too flat to drain reliably; 1 percent, ACI 362.1R minimum as built; 1/8 inch per foot, Michigan Concrete Association minimum; 1.5 percent, ACI 362.1R design minimum; 2 percent, IRC within 10 feet of a house; 1/4 inch per foot or 1:48, the ACI drainage minimum and the ADA maximum cross slope. The window for a walk is 1 percent to 1:48.

Design steeper than you need. ACI 362.1R, written for parking decks, asks for 1.5 percent in design so at least 1 percent survives construction and deflection. It's the only standard we found that separates the two.

Total fall by run at 1/8, 3/16 and 1/4 inch per foot
Total fall by run
Run1/8 in/ft3/16 in/ft1/4 in/ft
4 ft1/2 in3/4 in1 in
8 ft1 in1 1/2 in2 in
10 ft1 1/4 in1 7/8 in2 1/2 in
12 ft1 1/2 in2 1/4 in3 in
16 ft2 in3 in4 in
20 ft2 1/2 in3 3/4 in5 in
24 ft3 in4 1/2 in6 in
30 ft3 3/4 in5 5/8 in7 1/2 in

Inches per foot to percent and ratio

A quarter inch per foot is a little over 2 percent, not exactly 2. A true 2 percent is 0.24 inch per foot (0.02 × 12).

  • 1/8 in per ft

    1.04%

    1:96

  • 3/16 in per ft

    1.56%

    1:64

  • 1/4 in per ft

    2.08%

    1:48

  • 1/2 in per ft

    4.17%

    1:24

Full chart, 1/16 to 1 inch per foot, with degrees
Inches per foot converted to percent, ratio and degrees
In per ftPercentRatioDegrees
1/160.52%1:1920.30°
1/81.04%1:960.60°
3/161.56%1:640.90°
1/42.08%1:481.19°
5/162.60%1:38.41.49°
3/83.13%1:321.79°
1/24.17%1:242.39°
5/85.21%1:19.22.98°
18.33%1:124.76°

Part of the "2 percent" habit comes from ACI, which prints 1/4 inch per foot as 20 mm/m; the exact figure is 20.83. A gutter is far steeper than any slab: see the curb and gutter calculator.

Sidewalks: the drainage minimum is the ADA maximum

The ADA caps the cross slope of a walking surface at one inch in 48, which is exactly 1/4 inch per foot, ACI's drainage minimum. Build a walk at ACI's slope and you have no margin left under the ADA limit.

  • ADA and PROWAG

    1:48 max

    ADA 403.3, repeated as "1:48 (2.1%) maximum" in PROWAG R302.5.1.

  • Design at

    1%

    Barrier consultant Jean Tessmer's advice in The Construction Specifier, so the finished walk drains and stays under 1:48.

  • Tolerance

    +0.5%

    On curb ramp running slopes only, per a 2017 Colorado DOT memo, the only slope tolerance we found.

Why 1:48 drains: a 1971 Texas Transportation Institute study measured water depth on pavement at six cross slopes, and going from 1/16 to 1/4 inch per foot cut it by 62 percent, with smaller gains after that.

The concrete sidewalk calculator carries the PROWAG width and cross slope rules. For a slope you walk up, where 1:12 governs, use the ramp calculator.

What sloping the top costs in concrete

Pitching the top adds half the total fall to the average thickness. A 16 by 10 foot patio at 4 inches flat is 1.98 cubic yards; pitched from 4 to 8 inches it's 2.96.

  • 10 ft run

    +31%

    2.5 in of fall over a 4 in slab.

  • 20 ft run

    +63%

    5 in of fall, 6.5 in average.

  • 30 ft run

    +94%

    7.5 in of fall: nearly double.

All at 1/4 inch per foot with the low end held at 4 inches. The driveway calculator shows the same effect: 3.09 cubic yards for a flat 20 by 10 foot, 5 inch drive, 3.40 sloped from 5 to 6.

The opposite mistake is worse. Screed a fall into forms set for a flat 4 inches and the low end gets thin: over a 20 foot run at 1/4 inch per foot, holding a 4 inch average leaves 1.5 inches at the low edge, right where the water sits.

Slope the concrete, or slope the gravel?

Slope the gravel and keep the slab a constant thickness. You get the same drainage with no extra concrete.

Cross sections of a 16 foot run with 4 inches of fall. Pitching the top over a flat base makes the slab 4 inches at the low end and 8 at the high end, 50 percent more concrete. Pitching the gravel base keeps the slab 4 inches thick, with no extra concrete. Height drawn at about 6 times scale.

ACI 302.1R only says where the top goes. Field practice, as laid out in Fine Homebuilding, sets top-of-concrete elevations and subtracts the slab thickness to grade the base. On a narrow walk the base can't be graded that finely: ACI 117 allows the fine grade ±3/4 inch, a 1 1/2 inch band, more than the 1 inch of fall across a 4 foot walk. A low base costs you concrete: 18.8 percent more on a 4 inch slab, which the concrete calculator turns into the yards to order.

Pouring on a slope

Use a stiffer mix the steeper it gets, and broom across the fall. PCA Table 9-6 gives slabs a 1 to 3 inch slump, and the slope tells you where in that range to sit.

  • Slump

    1 to 3 in

    3 inches up to a 1-in-20 pitch, 1 to 2 inches on anything steeper, per Fine Homebuilding. How to mix concrete covers water and slump.

  • Finish

    Broom across

    Not a smooth trowel. How to pour a concrete slab covers screeding and floating.

  • Check it

    1 in on 4 ft

    Put a 1 inch shim under the downhill end of a 4 foot level. If the bubble centers, you have 1/4 inch per foot.

How flat is too flat

Below 1 percent as built, the ACI 362.1R floor, a slab stops draining reliably because construction tolerance and deflection eat the fall. Hot tub pads are the exception: makers want them nearly flat.

  • 1/16 in per ft

    0.52%

    Water "will not drain" at this slope or less, per engineers Salzano and Suprenant.

  • Hot tub pad

    0.42%

    Half an inch per 10 feet, Watkins' preferred pad slope. See hot tub pad.

Frequently asked questions

What is the minimum slope for a concrete slab to drain?

ACI 302.1R calls for a minimum of 1/4 inch per foot for positive drainage on exterior slabs. The Michigan Concrete Association accepts 1/8 inch per foot for driveways and sidewalks, so there is no single national figure.

Is 1/4 inch per foot the same as 2 percent?

Not quite. 1/4 divided by 12 is 2.08 percent, and a true 2 percent is 0.24 inches per foot. ACI rounds its own figure to 20 mm per meter, which is where "ACI says 2 percent" comes from.

How much extra concrete does a slope add?

Pitching the top over a flat base raises the average thickness by half the total fall. At 1/4 inch per foot on a 4 inch slab, that is 31 percent more concrete over a 10 foot run and 63 percent over 20 feet; pitching the base instead adds none.

How do I calculate the fall across a slab?

Multiply the run in feet by the slope in inches per foot: a 20 foot driveway at 1/4 inch per foot needs 5 inches of fall. To go the other way, divide the fall in inches by the run in feet.

Can a sidewalk meet both the drainage minimum and the ADA cross slope limit?

Only just. The ADA cross slope limit of 1:48 is exactly 1/4 inch per foot, so the drainage minimum and the accessibility maximum are the same number. Designers aim for about 1 percent to leave room for construction tolerance.

How do you pour concrete on a slope?

Grade the base to the slope so the slab stays a constant thickness, use a stiffer mix (1 to 2 inch slump) on pitches steeper than 1 in 20 so it does not slump downhill, and broom the finish across the fall for grip.